Sunday, October 30, 2005

Girder: Oct 22-30, 2005

On Oct 22 , I cut some 4X4's to 3 to 4 ft pieces and installed them on the post anchors. I held them close to a vertical position (using Ajmal's post level), and drove in a couple of 16d nails through the post & post anchors. I was concerned that there was some play between one of the anchors and the concrete pier. There was also some play between the posts and the anchors.

On Oct 27, Reddy and I strengthened some of the piers by mixing and applying concrete. We also used a water level to mark the joist line on all the posts.

On Oct 29, Reddy called up in the morning and asked why I was not working on the deck. He then showed up and we spent a tremendously fruitful Saturday morning! We accomplished a ton of things such as:
  1. Braced the posts to a perfectly vertical position using stakes and 2x4 s
  2. Sawed two 4x4 pieces and attached them to the center post using lag screws
  3. Attached 4 (four) girder beams to the posts. We used C-Clamps to hold them in place, and then applied screws for a more permanent hold.









0 Comments:

Post a Comment

<< Home